The school located in the Cap Hatien Circuit was destroyed by the 2018 Earthquake.
Cost to replace the school is $161,587.
Link to: Gran Fon School reconstruction budget:Gronfon Budget
Reconstruction of Gran Fon School
No | Item | Unit | Quantity | Unit Cost | Total Cost (US) | |
---|---|---|---|---|---|---|
1 | Mobilization | L. Sum | 1 | $5,000 | $5,000 | |
2 | Permits and Insurance | L. Sum | 1 | $2,500 | $2,500 | |
3 | Excavation | M3 | 109.72 | $10 | $1,097 | |
4 | Expanding and compacting | M3 | 138.84 | $12 | $1,666 | |
5 | Dry concrete | M3 | 7.2 | $10 | $72 | |
6 | Clean concrete | M3 | 5.1 | $300 | $1,530 | |
7 | Concrete Sole | M3 | 19.9 | $450 | $8,955 | |
8 | Concrete Base | M3 | 23.14 | $450 | $10,413 | |
9 | Concrete Beam | M3 | 6.52 | $450 | $2,934 | |
10 | Concrete Libage | M3 | 12.8 | $450 | $5,760 | |
11 | Concrete Column | M3 | 6.1 | $450 | $2,745 | |
12 | Floor concrete | M3 | 16.08 | $300 | $4,824 | |
13 | Block masonry | M2 | 253.74 | $40 | $10,149 | |
14 | Rock Masonry | M3 | 49.9 | $120 | $5,988 | |
15 | Stucco and Plaster | M2 | 507.48 | $30 | $15,224 | |
16 | Paint | M2 | 507.48 | $7 | $3,552 | |
17 | Roofing | M2 | 339.07 | $100 | $33,907 | |
18 | Sanitary block | FFT | 1 | $7,500 | $7,500 | |
19 | Doors | L.sumn | 6 | $300 | $1,800 | |
20 | Windows | U | 18 | $200 | $3,600 | |
21 | Polish Floor | M2 | 231.40 | $10 | $2,314 | |
22 | Outside Stairs | L.sumn | 1 | $600 | $600 | |
23 | Electric works | L.Sumn | 1 | $2,500 | $ 2,500 | |
24 | Plumbing | Unit | ||||
25 | Contingency | FFT | 1 | $8,000 | $8,000 | |
26 | Basic design fee | FFT | 1.00 | 6,000 | $6,000 | |
27 | Supervision and report | FFT | 1 | $15,000 | $15,000 | |
28 | EMH Fee | FFT | 1 | $ 125 | $ 125 | |
29 | Total | $161,587 | ||||
30 | Derly Charles | January 2019 | $161,587 |