Yvon School Expansion

Existing school at Yvon.

Plans are underway to expand the school at Yvon by adding two classrooms and a principal’s office.

PROJET DE CONSTRUCTION OF TWO CLASS ROOMS AND A PRINCIPAL OFFICE
BUDGET
NoDesignation des ouvragesUnit éQuantit éUnit costTotal cost(US)
1Implantation et MobilisationFFT1$1,500$1,500
0
2Fondation0
Fouillem370.2$25$1,755
Beton de propret ém32.97$300$891
Beton semelle isol éem310.8$450$4,860
Beton soclem33.74$400$1,496
Beton libagem36.96$450$3,132
3Maconnerie en rochem355.68$150$8,352
4Beton parquetm328.062507015
5ramblai et compactagem3130.94202618.8
6Elevation Murm2162.82203256.4
7Chainage intermediarem31.83400732
8chainage superieurem35.434002172
9Beton Colonnem31.56450702
10Crepissage et Enduissagem2393.54207870.8
11Lignesml44831344
12Cirage Parquetm21705850
13PortesU3300900
14FenetresU122002400
15Electricit éFFT110001000
16Toiturem2215.1110021511
17Peinturem2393.5451967.7
Sous-Total76325.7
Basic design feeFFT125002500
Supervision FeeFFT180008000
ContingencyFFT115001500
TOTAL BUDGET88325.7
Revised July,2019
Derly Charles