PROJET DE CONSTRUCTION DE L’EGLISE METHODISTE DE MIZAC
BUDGET

No Item Unit Quantity Unit Cost Total Cost (US) Phase 1(US)
1 Mobilization L. Sum $1,500 $1,500
2 Excavation M3 21.7 40 $868 $868
3 Cleanliness concrete M3 1.73 300 $519 $519
4 Footing M3 3.05 400 1,200 1,200
5 Masonry of Rock M3 72.7 120 $8,724 $8,724
6 Pedestral Concrete M3 8.5 400 $3,400 $3,400
7 Backfill and compaction M3 281.08 20 $5,621.60
8 Floor concrete M3 16.08 300 $4,824
9 Column concrete M3 6.84 400 $2,736
10 Block masonry M2 190 30 $5,700
11 Clamping wall (Chainage) M3 5.62 300 $1,686
12 Coating( Crepissage-enduissage) M2 494.2 15 $7,413
13 windows reinforcement M3 1 400 $400
14 Choir (Chaire) L.sumn $1,500
15 Sacristy slab and front porch M3 6.5 600 3,900
16 bathroom ditch(fosse ) L.sumn $1,000
17 Floor polish M2 146.7 8 $1,173.60
18 Roofing M2 162 60 $9,720
19 Plombing L.sumn $1,500
20 Electric works L.Sumn $ 2,000
21 Windows Unit 11 40 $4,400
22 Doors Unit 6 300 $1,800
23 Bathroom tiles M2 40 40 $1,600
24 Steps at the front L.sumn $300
20 Subtotal $73,485
21 Study cost $5,000 $2,000
22 Engineer Fee $11,022.75 $1,621.10
23 Total $89,508 $19,832